In the CPM technique, the critical path slack is:

This question was previously asked in
RRB JE ME 22 Apr 2025 Shift 2 CBT 2 Official Paper
View all RRB JE Papers >
  1. zero
  2. negative
  3. either negative or zero
  4. positive

Answer (Detailed Solution Below)

Option 1 : zero
Free
General Science for All Railway Exams Mock Test
2.1 Lakh Users
20 Questions 20 Marks 15 Mins

Detailed Solution

Download Solution PDF

Explanation:

Critical Path Method (CPM):

  • The Critical Path Method (CPM) is a project management technique used to determine the sequence of activities that directly affect the project completion time. It identifies the longest path of dependent activities in the project schedule, known as the critical path. The duration of this path determines the shortest possible project completion time.

Critical Path and Slack:

  • The critical path in a project is defined as the sequence of tasks where any delay in one task would directly result in a delay in the overall project completion. The slack (or float) is the amount of time an activity can be delayed without affecting the project’s completion date. For activities on the critical path, the slack is zero because there is no flexibility to delay these activities without impacting the entire project.

Why Slack on the Critical Path is Zero:

  • The critical path represents the longest duration path in the project network. If any activity on this path is delayed, the entire project completion time will also be delayed.
  • Slack is calculated as the difference between the latest allowable finish time (LF) and the earliest finish time (EF) of an activity:
    Slack = LF - EF
  • For activities on the critical path, the LF equals EF because they determine the project’s end date. Therefore, their slack is zero.
Latest RRB JE Updates

Last updated on Jun 16, 2025

-> RRB JE CBT 2 answer key 2025 for June 4 exam has been released at the official website.

-> Check Your Marks via RRB JE CBT 2 Rank Calculator 2025

-> RRB JE CBT 2 admit card 2025 has been released. 

-> RRB JE CBT 2 city intimation slip 2025 for June 4 exam has been released at the official website.

-> RRB JE CBT 2 Cancelled Shift Exam 2025 will be conducted on June 4, 2025 in offline mode. 

-> RRB JE CBT 2 Exam Analysis 2025 is Out, Candidates analysis their exam according to Shift 1 and 2 Questions and Answers.

-> The RRB JE Notification 2024 was released for 7951 vacancies for various posts of Junior Engineer, Depot Material Superintendent, Chemical & Metallurgical Assistant, Chemical Supervisor (Research) and Metallurgical Supervisor (Research). 

-> The selection process includes CBT 1, CBT 2, and Document Verification & Medical Test.

-> The candidates who will be selected will get an approximate salary range between Rs. 13,500 to Rs. 38,425.

-> Attempt RRB JE Free Current Affairs Mock Test here

-> Enhance your preparation with the RRB JE Previous Year Papers

More Operations Research Questions

Get Free Access Now
Hot Links: teen patti joy official teen patti master gold download teen patti all app teen patti game paisa wala