Question
Download Solution PDFMatch List I with List II
LIST I (Project Network concepts) |
LIST II (Underlying meaning) |
||
A. | Crashing an activity | I. | Length of the longest path through the project network |
B. | Project Network | II. | It shows the time and cost when the activity is fully crashed |
C. | Critical path | III. | It consists of a number of nodes and a number of arcs that connects two different nodes |
D. | Crash point | IV. | Taking special (costly) measures to reduce the duration of an activity below its normal value |
Choose the correct answer from the options given below:
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFThe correct answer is A - IV, B - III, C - I, D - II.
Key Points
The correct sequence is:
A. Crashing an activity - IV. Taking special (costly) measures to reduce the duration of an activity below its normal value
Crashing an activity refers to the process of shortening the duration of an activity in a project. It involves taking special measures, which can be costly, to expedite the completion of the activity. These measures may include adding more resources, working overtime, or using specialized equipment to accelerate the work. Crashing an activity allows for a shorter overall project duration but often comes with additional costs.
B. Project Network - III. It consists of a number of nodes and a number of arcs that connect two different nodes
A project network is a graphical representation of the activities and their dependencies within a project. It consists of nodes, which represent the activities, and arcs, which connect the nodes to show the logical sequence and dependencies between the activities. The project network helps visualize the flow of work and the relationships among activities, aiding in project planning, scheduling, and monitoring.
C. Critical path - I. Length of the longest path through the project network
The critical path in a project network is the longest path from the project's start to its end. It determines the minimum amount of time required to complete the project. Any delay in activities along the critical path will directly impact the overall project timeline. Identifying the critical path is essential for project scheduling and resource allocation, as it helps in prioritizing activities that are critical for the project's timely completion.
D. Crash point - II. It shows the time and cost when the activity is fully crashed
The crash point represents the time and cost associated with fully crashing an activity in a project. Fully crashing an activity means reducing its duration to the shortest possible time by applying all available resources and measures. The crash point helps in evaluating the impact of crashing activities on project timelines and costs. It provides insights into the trade-offs between time and cost when accelerating specific activities in a project.
Hence, the correct answer is A - IV, B - III, C - I, D - II.
Last updated on Jun 6, 2025
-> The UGC NET Exam Schedule 2025 for June has been released on its official website.
-> The UGC NET Application Correction Window 2025 is available from 14th May to 15th May 2025.
-> The UGC NET 2025 online application form submission closed on 12th May 2025.
-> The June 2025 Exam will be conducted from 21st June to 30th June 2025
-> The UGC-NET exam takes place for 85 subjects, to determine the eligibility for 'Junior Research Fellowship’ and ‘Assistant Professor’ posts, as well as for PhD. admissions.
-> The exam is conducted bi-annually - in June and December cycles.
-> The exam comprises two papers - Paper I and Paper II. Paper I consists of 50 questions and Paper II consists of 100 questions.
-> The candidates who are preparing for the exam can check the UGC NET Previous Year Papers and UGC NET Test Series to boost their preparations.