Download Solution PDFWhich one of the following schedules shows the specific activities necessary to complete an activity or work package?
This question was previously asked in
UPSC ESE 2019 Paper 1
Answer (Detailed Solution Below)
Option 3 : Task schedule
Free Tests
View all Free tests >
ST 1: UPSC ESE (IES) Civil - Building Materials
6.1 K Users
20 Questions
40 Marks
24 Mins
Detailed Solution
Download Solution PDFExplanation:
Work break down structure
Work break down (WBD) defines each deliverable and the decomposition of the deliverable into work packages.
Plan—Program—Project—Sub-project—Activity—Work—Task
- Task schedule deals with allocation of resources related to work package as well activity.
- When the project activities have been defined, they are broken down into tasks and after time & resource allocation, task schedules are prepared which is specified activities necessary to complete a work package.
Last updated on May 28, 2025
-> UPSC ESE admit card 2025 for the prelims exam has been released.
-> The UPSC IES Prelims 2025 will be held on 8th June 2025.
-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.
-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.