Question
Download Solution PDFIn a work-breakdown structure, the _________ approach to planning is adopted
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
Work Breakdown Structure
- It defined as a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables.
- It organizes and defines the total scope of the project.
- Each descending level i.e. Top-Down approach represents an increasingly detailed definition of the project work.
- The intelligent structure of breakdown is a precursor to effective project management.
- The WBS is the key tool to assist the project manager in defining the work to be performed to meet the objectives of a project.
- The WBS provides the framework on which costs, time, and schedule can be compared against the budget for each level of the WBS.
Last updated on May 19, 2025
-> JKSSB Junior Engineer recruitment exam date 2025 for Civil and Electrical Engineering has been released on its official website.
-> JKSSB JE exam will be conducted on 10th August (Civil), and on 27th July 2025 (Electrical).
-> JKSSB JE recruitment 2025 notification has been released for Civil Engineering.
-> A total of 508 vacancies has been announced for JKSSB JE Civil Engineering recruitment 2025.
-> JKSSB JE Online Application form will be activated from18th May 2025 to 16th June 2025
-> Candidates who are preparing for JKSSB JE can download syllabus PDF from official website of JKSSB.
-> The candidates can check the JKSSB JE Previous Year Papers to understand the difficulty level of the exam.
-> Candidates also attempt the JKSSB JE Mock Test which gives you an experience of the actual exam.