Question
Download Solution PDFA simple project comprises of two start-to-end parallel paths, each with three activities in series, with no interpath dependencies. The a, m, b data (in days) for each activity are shown in the diagram. Assuming that three activities in series are enough for further computations, what will be the total project duration and its standard deviation?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
Here two path – (I) ⇒ 1 – 2 – 4 – 6
(II) ⇒ 1 – 3 – 5 – 6
Calculation of expected time for both path –
\({T_e} = \frac{{{T_0} + 4{T_m} + {T_p}}}{6}\)
For I
\( \Rightarrow \frac{{2 + 4 \times 3 + 4}}{6} + \frac{{4 + 4 \times 6 + 8}}{6} + \frac{{5 \times 4 \times 8 + 11}}{6}\)
= 3 + 6 + 8
= 17 days
For II
\( \Rightarrow \frac{{6 + 4 \times 7 + 8}}{6} + \frac{{12 + 4 \times 12 + 18}}{6} + \frac{{9 + 4 \times 15 + 18}}{6}\)
= 7 + 13 + 14.5
\( = 34\frac{1}{2}{\rm{\;days}}\)
Hence longest path II so it is critical standard deviation.
\(\delta d = \sqrt {\sum {{\left( {\frac{{{T_p} - {T_0}}}{6}} \right)}^2}} \)
\(\sigma = \sqrt {{{\left( {\frac{{8 - 6}}{6}} \right)}^2} + {{\left( {\frac{{18 - 12}}{6}} \right)}^2} + {{\left( {\frac{{18 - 9}}{6}} \right)}^2}} \)
\(\sigma = \sqrt {{{\left( {\frac{1}{3}} \right)}^2} + 1 + {{\left( {\frac{3}{2}} \right)}^2}} = \sqrt {\frac{1}{9} + 1 + \frac{9}{4}} = \sqrt {\frac{{121}}{{36}}} \)
\(\therefore \;\left[ {\sigma = \frac{{11}}{6}\;days} \right]\)
Last updated on May 28, 2025
-> UPSC ESE admit card 2025 for the prelims exam has been released.
-> The UPSC IES Prelims 2025 will be held on 8th June 2025.
-> The selection process includes a Prelims and a Mains Examination, followed by a Personality Test/Interview.
-> Candidates should attempt the UPSC IES mock tests to increase their efficiency. The UPSC IES previous year papers can be downloaded here.