Work and Wages MCQ Quiz - Objective Question with Answer for Work and Wages - Download Free PDF
Last updated on May 12, 2025
Latest Work and Wages MCQ Objective Questions
Work and Wages Question 1:
P, Q and R can complete a work in 24, 30 and 40 days respectively. Total wage of a work is Rs. _______ . P works for ____ days alone then Q works for 4 days alone and the rest of the work is done by P, Q and R together. Difference between the wage of P and R is Rs. _______. Find which of the following is true?
Answer (Detailed Solution Below)
Work and Wages Question 1 Detailed Solution
Calculation
For option 3),
P, Q and R can complete a work in 24, 30 and 40 days respectively.
So, total work = LCM of 24, 30 and 40 = 120 unit
So, Efficiency of P, Q and R is 5, 4 and 3 respectively.
[Efficiency = total work / total number of days]
P works for 4 days alone.
So, P did 4 × 5 = 20 unit of work.
Q did 4 × 4 = 16 unit of work
Rest work 120 - 20 – 16 = 84
They together complete the work in 84 / [ 5 + 4 +3] = 7
Wage for per unit work is 3480 / 120 = 29
P did = 20 + 7 × 5 = 55 unit of work.
R did 7 × 3 = 21 unit of work
So, difference between wage P and R is [ 55 – 21] × 29 = 986
So, Option 3) is satisfy.
Work and Wages Question 2:
The amount of money earned on a job is directly proportional to the number of hours worked. If ₹324 is earned in 6 hours, then how much money (in ₹) will be earned in 29 hours of work?
Answer (Detailed Solution Below)
Work and Wages Question 2 Detailed Solution
Given:
Money earned for 6 hours of work = ₹324
Number of hours worked = 29 hours
Formula Used:
Money earned is directly proportional to the number of hours worked.
M = k × H
where M is the money earned, H is the number of hours, and k is the proportionality constant.
Calculation:
First, find the proportionality constant k :
k = M/H
⇒ k = 324/6
⇒ k = 54
Now, calculate the money earned for 29 hours of work:
M = k × H
⇒ M = 54 × 29
⇒ M = 1,566
The amount of money earned in 29 hours is ₹1,566.
Work and Wages Question 3:
Ram can do a work in 20 days. Ram and Shyam together can do the same work in 15 days. If they are paid Rs.400 for that work, what is the share of Shyam (in Rs.).
Answer (Detailed Solution Below)
Work and Wages Question 3 Detailed Solution
Given:
Ram alone can do the work in = 20 days
Ram and Shyam together can do the work in = 15 days
Total payment for the work = Rs.400
Formula used:
Efficiency = Total work / Days
Shyam’s share = (Shyam's efficiency / Total efficiency) × Total payment
Calculations:
Total work (LCM of 20, 15) = 60 units
Efficiency of Ram = 60 / 20 = 3 units/day
Efficiency of (Ram + Shyam) = 60 / 15 = 4 units/day
Efficiency of Shyam = Efficiency of (Ram + Shyam) - Efficiency of Ram
Efficiency of Shyam = 4 - 3 = 1 unit/day
Share of payment is divided based on efficiency:
Total efficiency = 4 units/day
Shyam’s share = (Shyam's efficiency / Total efficiency) × Total payment
Shyam’s share = (1 / 4) × 400 = Rs.100
Shyam's share is Rs.100.
Work and Wages Question 4:
A man and a boy complete a piece of work in 10 days and are paid Rs 10,000. The man is 50% more efficient than the boy. What is the difference between the daily wages of the man and the boy?
Answer (Detailed Solution Below)
Work and Wages Question 4 Detailed Solution
Given:
Total days = 10 days
Total payment = Rs. 10,000
Man is 50% more efficient than boy.
Formula used:
Efficiency ratio = Work ratio = Wage ratio
Calculations:
Efficiency ratio (Man : Boy) = 150 : 100 = 3 : 2
Work ratio (Man : Boy) = 3 : 2
Wage ratio (Man : Boy) = 3 : 2
Total ratio = 3 + 2 = 5
Total daily wage = 10000 / 10 = 1000
Man's daily wage ratio = 3/5
Boy's daily wage ratio = 2/5
Man's daily wage = (3/5) × 1000 = Rs. 600
Boy's daily wage = (2/5) × 1000 = Rs. 400
Difference = 600 - 400 = Rs. 200
∴ The difference between the daily wages of the man and the boy is Rs. 200.
Work and Wages Question 5:
Sonu and Monu undertake to do a piece of work for ₹ 3,600. Sonu along can do it in 6 days while Monu alone can do it in 8 days. With the help of Ramu, they finish it in 3 days. The share of Ramu (in ₹) will be:
Answer (Detailed Solution Below)
Work and Wages Question 5 Detailed Solution
CONCEPT:
Work and Time
- The amount of work done is inversely proportional to the number of days when the amount of work is constant.
- If two or more persons work together, their combined work per day is the sum of their individual work rates.
EXPLANATION:
- First, let's find out the work rates of Sonu and Monu:
- Sonu can complete the work in 6 days, so his work rate is 1/6 of the work per day.
- Monu can complete the work in 8 days, so his work rate is 1/8 of the work per day.
- When Sonu, Monu, and Ramu work together, they complete the work in 3 days. Let's denote Ramu's work rate as R (work per day).
- The combined work rate of Sonu, Monu, and Ramu is (1/6) + (1/8) + R.
- The total work is completed in 3 days, so their combined work rate is 1/3 of the work per day.
- (1/6) + (1/8) + R = 1/3
- (4/24) + (3/24) + R = (8/24)
- (7/24) + R = (8/24)
- R = (8/24) - (7/24)
- R = 1/24
- Ramu's work rate is 1/24 of the work per day. Therefore, in 3 days, Ramu does 3 * (1/24) = 1/8 of the total work.
- The total payment for the work is ₹3600. Therefore, Ramu's share of the payment is (1/8) * 3600 = ₹450.
Therefore, the share of Ramu (in ₹) will be ₹450.
Top Work and Wages MCQ Objective Questions
A and B together are supposed to do 13/15 of the work and B and C together 11/20 of the work. If the difference between wages of A and C is Rs. 7600, then the total wages of A and C is:
Answer (Detailed Solution Below)
Work and Wages Question 6 Detailed Solution
Download Solution PDFGiven:
Difference between wages of A and C = Rs. 7600
Formula Used:
Share in wages = Work done/Total work × Total wages
Calculation:
Let total work be 60 unit,
Work done by A and B = 13/15 × 60 = 52 unit
⇒ Work done by C = 60 – 52 = 8 unit
Work done by B and C = 11/20 × 60 = 33 unit
⇒ Work done by A = 60 – 33 = 27 unit
Work done by B = 60 – 27 – 8 = 25 unit
According to the question,
27 – 8 = 19 unit = 7600
⇒ 1 unit = 400
Total wages of A and C = (27 + 8) = 35 units = 35 × 400 = Rs. 14000
In a camp, there is a meal for 120 men or 200 children. If 150 children have taken the meal, how many men will be catered-to with remaining meal?
Answer (Detailed Solution Below)
Work and Wages Question 7 Detailed Solution
Download Solution PDFGiven:
In a camp there is a meal for 120 men or 200 children.
Calculation:
According to the question, 150 children have taken the meal
So, 50 children left
⇒ 200 children = 120 men
⇒ 50 = 120 × (\(\frac{50}{200}\)) men
⇒ 30 men
∴ 30men will be catered-to with remaining meal.
5 women and 9 girls earn a total of ₹18,720 in 9 days, while 9 women and 16 girls earn a total of ₹ 52,080 in 14 days. How much will 12 women and 7 girls together earn (in ₹) in 13 days?
Answer (Detailed Solution Below)
Work and Wages Question 8 Detailed Solution
Download Solution PDFGiven:
5 women and 9 girls can earn Rs.18,720 in 9 days
9 women and 16 girls earn a total of ₹ 52,080 in 14 days
Concept:
Total work = number of workers doing work × time taken to complete the work.
(5W + 9G) × 9 = 18,720
⇒ (5W + 9G) = 2080 ----(i)
(9W + 16G) × 14 = 52080
⇒ (9W + 16G) = 3720 ----(ii)
solving equations (i) and (ii)
⇒ 45W + 81G = 18720 ---- (iii)
⇒ 45W + 80G = 18600 ---- (iv)
by subtraction equations (iii) and (iv)
⇒ 1G = Rs. 120
Putting the value of G in equation (i)
⇒ 5W + 1080 = 2080
⇒ 5W = 1000
⇒ W = Rs.200
According to the question:
Money earned by 12 women and 7 girls in 13days
⇒ (12 × 200 + 7 × 120) × 13
⇒ (2400 + 840) × 13
⇒ 3240 × 13 = 42120
∴ The required value is 42120.
A firm reduced employees in the ratio 12 ∶ 5 in time of inflation, and the average wage per employee increased in the ratio 9 ∶ 17. By doing so, the firm saved Rs.46,000. What was the initial expenditure (in Rs) of the firm?
Answer (Detailed Solution Below)
Work and Wages Question 9 Detailed Solution
Download Solution PDFFormula Used:
Expenditure = number of employee × average wage
Calculation:
Let the number of employee of the firm be 12x and 5x pre and post reduction respectively.
and average salary be 9y and 17 y pre and post reduction respectively.
Expenditure before reduction is 12x × 9y
Expenditure after reduction is 5x × 17y
ATQ: 12x × 9y - 5x × 17y = 46000
⇒ (108 - 85)xy = 46000
⇒ 23xy = 46000
⇒ xy = 2000
Expenditure before reduction is 12x × 9y = 108 × xy = 108 × 2000 = 216000
Expenditure before reduction is Rs. 216000.
4 men and 6 women get Rs. 1600/- by doing a piece of work in 5 days, 3 men and 7 women get Rs. 1740/- by doing the same work in 6 days. In how many days 7 men and 6 women can complete the same work getting Rs. 3760/-
Answer (Detailed Solution Below)
Work and Wages Question 10 Detailed Solution
Download Solution PDFGiven:
4 men and 6 women get Rs. 1600/- by doing a piece of work in 5 days
3 men and 7 women get Rs. 1740/- by doing the same work in 6 days
7 men and 6 women can complete the same work getting Rs. 3760/-
Calculation:
Let,
M as the rate at which one man can complete the work (in Rs./day)
W as the rate at which one woman can complete the work (in Rs./day)
From the given problem, we have two equations:
4M + 6W = 1600/5 ------- (equation 1)
3M + 7W = 1740/6 ------- (equation 2)
First, multiply equation (1) by 3 and equation (2) by 4:
12M + 18W = 960 ------- (equation 3)
12M + 28W = 1160 ------- (equation 4)
Equation (4) - Equation (3)
10W = 200
⇒ W = 200 / 10 = Rs. 20/day
Substitute W into equation (1):
4M + 6 × 20 = 320
⇒ M = 200 / 4 = Rs. 50/day
Now,
Work = Rate × Time
3760 = (7M + 6W) × Time
3760 = (7 × 50 + 6 × 20) × Time
3760 = (350 + 120) × Time
3760 = 470 × Time
Time = 3760 / 470 = 8 days
∴ Required number of days = 3760/470 = 8 days.
Shortcut Trick
Calculation:
⇒ \((M_1 ~+~W_1)× D_1\over (Income)_1\) = \((M_2 ~+ ~W_2) D_2\over (Income)_2\)
⇒ \((4m +6w)× 5\over 1600\) = \((3m + 7w)× 6\over 1740\)
⇒ \(4m +6w\over 3m + 7w\) = \(1600×6\over 1740×5 \)
⇒ 20 m = 50 w
⇒ m : w = 5 : 2
Now, put the respective ratio in the equation:
⇒ \((4m +6w)× 5\over 1600\) = [(4 × 5 + 6 × 2) × 5]/1600 = 1/10
According to the question:
⇒ \((7m + 6w)× 6\over 1740\) = [(7 × 5 + 6 × 2)× d]/3760
⇒ 1/10 = d/80
Required number of days = 80/10 = 8 days
∴ The correct answer is 8 days.
15 persons have taken a job of digging a pond in 20 days. 5 persons have left after 10 days. Again after 5 days 5 more have left. How many days would be required to complete the job?
Answer (Detailed Solution Below)
Work and Wages Question 11 Detailed Solution
Download Solution PDFGIVEN:
Time taken by 15 people to dig the pond = 20 days
FORMULA USED:
Man – day formula
(m1 × d1 × h1)/w1 = (m2 × d2 × h2)/w2
Where m1, m2 is number of persons working
d1, d2 is number of days taken
h1, h2 is number of hours
w1, w2 is the units of work done
CALCULATION:
15 persons have taken a job of digging a pond in 20 days
Total work = 15 × 20 = 300 units
Work done by 15 men in 10 days = 15 × 10 = 150 units
Now,
5 men left the work
Work done by 10 men in 5 days = 10 × 5 = 50 units
Again 5 men left the work
Remaining work = 300 – (150 + 50) = 100 units
⇒ Remaining work will be done in 100/5 = 20 days
∴ Total number of days taken to complete the work = 10 + 5 + 20 = 35 days
A and B undertake to do a job for Rs. 6,000. A can do it in 10 days and B can do it in 12 days. With the assistance of C, they finish the work in 4 days. How much should C be paid for his work?
Answer (Detailed Solution Below)
Work and Wages Question 12 Detailed Solution
Download Solution PDFGiven:-
A can do a work in 10 days
B can do a work in 12 days
they undertake to do job for Rs. 6000
Concept used:-
Efficiancy concept related to work and time.
Total work = LCM(Time taken by all individual)
Calculation:-
Total work = LCM(10, 12)
Total work = 60 units
Rs. per unit = 6000/60 = 100 Rs. per unit
∴ A's per day work = 60/10 = 6 units
A's per day income = 6 × 100 = Rs. 600
B's per day work = 60/12 = 5 units
B's per day income = 5 × 100 = Rs. 500
Let C's per day work = x units
According to Question-
⇒ (6 × 4) + (5 × 4) + (x × 4) = 60
⇒ 24 + 20 + 4x = 60
⇒ 4x = 60 - 44
⇒ x = 16/4
⇒ x = 4 units
C's per day income = 4 × 100 = Rs. 400
∴ C should be paid for work = 400 × 4 = Rs.1600
A can do a piece of work in 20 days while B can do it in 30 days. They work together for 10 days and the rest of the work is done by C in 5 days. If they get Rs 560 for the whole work, how much money will A get?
Answer (Detailed Solution Below)
Work and Wages Question 13 Detailed Solution
Download Solution PDFGiven:
Time is taken by A to do the work = 20 days
Time is taken by B to do the work = 30 days
Total wage = Rs. 560
Formula used:
Time = Total work/Efficiency
Concept used:
Wage is divided the same as efficiency and inversely proportional to the time taken
Calculation:
Work done by A in 1 day is = 1/20
Work done by B in 1 day is = 1/30
Work done by A and B together in 1 day is = (1/20 + 1/30) = 1/12
Work is done by A and B together in 10 days is = 10/12
Remaining work = 1 – 10/12 = 2/12 = 1/6
C do 1/6 of the work in 5 days
Total work done by C alone in 5 × 6 is = 30 days
Wages ratio of A, B and C = 1/20 × 10 : 1/30 × 10 : 1/30 × 5 = 6 : 4 : 2
Money A will get = 6/12 × 560 = 280
∴ Share of money A will get is Rs 280
Shortcut Trick
Since A can do that piece of work in 20 days and has worked for 10 days
i.e. A has done half of total work.
So A will get half of the amount paid to all i.e. = 560/2 = Rs. 280
Confusion Points
You may think that 240 is the correct answer but it is not.
It is so because the time for which C has worked is 5 days whereas A and B have worked for 10 days.
Thus, Wages ratio of A, B and C = 1/20 × 10 : 1/30 × 10 : 1/30 × 5 = 6 : 4 : 2
If 15 boys earn Rs. 750 in 5 days, then how much money 25 boys will earn in 6 days?
Answer (Detailed Solution Below)
Work and Wages Question 14 Detailed Solution
Download Solution PDFGiven:-
15 boys for 5 days = at Rs 750
Calculation:-
Let 25 boys earn Rs. x in 6 days,
then according to question,
⇒ (15 × 5)/750 = (25 × 6)/x
⇒ x = 150 × 10
⇒ x = 1500
∴ 25 boys will earn Rs. 1500 in 6 daysSamir and Puneet can complete the same work in 10 days and 15 days respectively. The work was assigned for Rs.4500. After working together for 3 days Samir and Puneet involved Ashok. The work was completed in total 5 days. What amount (in Rs.) was paid to Ashok?
Answer (Detailed Solution Below)
Work and Wages Question 15 Detailed Solution
Download Solution PDFGiven:
Samir's 1 day's work = 1/10
Puneet's 1 day's work = 1/15
Calculation:
(Samir + Puneet)'s 1 day's work = 1/10 + 1/15 = 1/6
(Samir + Puneet)'s 3 days work = 3 × 1/6 = 1/2
Remaining work after 3 days = 1 - 1/2 = 1/2
Remaining work completed in 2 days.
(Samir + Puneet + Ashok)'s 1 day's work = 1/2 × 1/2 = 1/4
Ashok's 1 day's work = 1/4 - 1/6 = 1/12
Ratio of work done = 5/10 : 5/15 : 2/12
= 1/2 : 1/3 : 1/6
= 3 : 2 : 1
∴ Ashok's share = 1/6 × 4500 = Rs.750
Alternate Method Samir and Puneet can complete the same work in 10 days and 15 days respectively
Total work = LCM(10, 15) = 30 units
Efficiency of Samir = 30/10 = 3 units
Efficiency of Puneet = 30/15 = 2 units
According to the question,
Samir and Puneet worked for (3 + 2) = 5 days
Work done by Samir and Puneet in 5 days = 5 × 5 = 25 units
Remaining 5 units of work is done by Ashok in 2 days
Efficiency of Ashok = 5/2 = 2.5 units
Total amount = Rs. 4500
Amount given for 1 unit of work = 4500/30 = 150
Amount given to Ashok = 150 × 5 = Rs. 750