Work and Wages MCQ Quiz - Objective Question with Answer for Work and Wages - Download Free PDF

Last updated on May 12, 2025

Work and wages is a crucial part of various entrance exams and placement recruitments such as Bank PO, Railway Exams,etc. It is requisite to have a good grasp on Work and Wages Questions. In this article, Testbook has formatted some Work and Wages MCQs Quiz followed by their solutions and detailed explanations. Along with this, some tips and tricks for the Work and Wages section are also mentioned to boost your preparation for this particular section.

Latest Work and Wages MCQ Objective Questions

Work and Wages Question 1:

P, Q and R can complete a work in 24, 30 and 40 days respectively. Total wage of a work is Rs. _______ . P works for ____ days alone then Q works for 4 days alone and the rest of the work is done by P, Q and R together. Difference between the wage of P and R is Rs. _______. Find which of the following is true?

 

  1. 5640, 4, 456
  2. 4920, 5, 255
  3. 3480,4,986
  4. 4440, 4, 240

Answer (Detailed Solution Below)

Option 3 : 3480,4,986

Work and Wages Question 1 Detailed Solution

Calculation

For option 3),

P, Q and R can complete a work in 24, 30 and 40 days respectively.

So, total work = LCM of 24, 30 and 40 = 120 unit

So, Efficiency of P, Q and R is 5, 4 and 3 respectively.

[Efficiency = total work / total number of days]

P works for 4 days alone.

So, P did 4 × 5 = 20 unit of work.

Q did 4 × 4 = 16 unit of work

Rest work 120 - 20 – 16 = 84

They together complete the work in  84 / [ 5 + 4 +3] = 7

Wage for per unit work is 3480 / 120 = 29

 P did = 20 + 7 × 5 = 55 unit of work.

R did 7 × 3 = 21 unit of work

So, difference between wage P and R is [ 55 – 21] × 29 = 986

So, Option 3) is satisfy. 

Work and Wages Question 2:

The amount of money earned on a job is directly proportional to the number of hours worked. If ₹324 is earned in 6 hours, then how much money (in ₹) will be earned in 29 hours of work? 

  1. ₹1,566 
  2. ₹1,655
  3. ₹1,585 
  4. ₹1,676

Answer (Detailed Solution Below)

Option 1 : ₹1,566 

Work and Wages Question 2 Detailed Solution

Given:

Money earned for 6 hours of work = ₹324

Number of hours worked = 29 hours

Formula Used:

Money earned is directly proportional to the number of hours worked.

M = k × H

where M is the money earned, H is the number of hours, and k is the proportionality constant.

Calculation:

First, find the proportionality constant k :

k = M/H

⇒ k = 324/6

⇒ k = 54

Now, calculate the money earned for 29 hours of work:

M = k × H

⇒ M = 54 × 29

⇒ M = 1,566

The amount of money earned in 29 hours is ₹1,566.

Work and Wages Question 3:

Ram can do a work in 20 days. Ram and Shyam together can do the same work in 15 days. If they are paid Rs.400 for that work, what is the share of Shyam (in Rs.).

  1. 100
  2. 200
  3. 150
  4. 50

Answer (Detailed Solution Below)

Option 1 : 100

Work and Wages Question 3 Detailed Solution

Given:

Ram alone can do the work in = 20 days

Ram and Shyam together can do the work in = 15 days

Total payment for the work = Rs.400

Formula used:

Efficiency = Total work / Days 

Shyam’s share = (Shyam's efficiency / Total efficiency) × Total payment

Calculations:

Total work (LCM of 20, 15) = 60 units

Efficiency of Ram = 60 / 20 = 3 units/day

Efficiency of (Ram + Shyam) = 60 / 15 = 4 units/day

Efficiency of Shyam = Efficiency of (Ram + Shyam) - Efficiency of Ram

Efficiency of Shyam = 4 - 3 = 1 unit/day

Share of payment is divided based on efficiency:

Total efficiency = 4 units/day

Shyam’s share = (Shyam's efficiency / Total efficiency) × Total payment

Shyam’s share = (1 / 4) × 400 = Rs.100

Shyam's share is Rs.100.

Work and Wages Question 4:

A man and a boy complete a piece of work in 10 days and are paid Rs 10,000. The man is 50% more efficient than the boy. What is the difference between the daily wages of the man and the boy?

  1. Rs 100 
  2. Rs 500 
  3. Rs 400 
  4. Rs 200 

Answer (Detailed Solution Below)

Option 4 : Rs 200 

Work and Wages Question 4 Detailed Solution

Given:

Total days = 10 days

Total payment = Rs. 10,000

Man is 50% more efficient than boy.

Formula used:

Efficiency ratio = Work ratio = Wage ratio

Calculations:

Efficiency ratio (Man : Boy) = 150 : 100 = 3 : 2

Work ratio (Man : Boy) = 3 : 2

Wage ratio (Man : Boy) = 3 : 2

Total ratio = 3 + 2 = 5

Total daily wage = 10000 / 10 = 1000

Man's daily wage ratio = 3/5

Boy's daily wage ratio = 2/5

Man's daily wage = (3/5) × 1000 = Rs. 600

Boy's daily wage = (2/5) × 1000 = Rs. 400

Difference = 600 - 400 = Rs. 200

∴ The difference between the daily wages of the man and the boy is Rs. 200.

Work and Wages Question 5:

Sonu and Monu undertake to do a piece of work for ₹ 3,600. Sonu along can do it in 6 days while Monu alone can do it in 8 days. With the help of Ramu, they finish it in 3 days. The share of Ramu (in ₹) will be:

  1. 1350
  2. 900
  3. 1200
  4. 450

Answer (Detailed Solution Below)

Option 4 : 450

Work and Wages Question 5 Detailed Solution

CONCEPT:

Work and Time

  • The amount of work done is inversely proportional to the number of days when the amount of work is constant.
  • If two or more persons work together, their combined work per day is the sum of their individual work rates.

EXPLANATION:

  • First, let's find out the work rates of Sonu and Monu:
    • Sonu can complete the work in 6 days, so his work rate is 1/6 of the work per day.
    • Monu can complete the work in 8 days, so his work rate is 1/8 of the work per day.
  • When Sonu, Monu, and Ramu work together, they complete the work in 3 days. Let's denote Ramu's work rate as R (work per day).
    • The combined work rate of Sonu, Monu, and Ramu is (1/6) + (1/8) + R.
    • The total work is completed in 3 days, so their combined work rate is 1/3 of the work per day.
  • (1/6) + (1/8) + R = 1/3
  • (4/24) + (3/24) + R = (8/24)
    • (7/24) + R = (8/24)
    • R = (8/24) - (7/24)
    • R = 1/24
  • Ramu's work rate is 1/24 of the work per day. Therefore, in 3 days, Ramu does 3 * (1/24) = 1/8 of the total work.
  • The total payment for the work is ₹3600. Therefore, Ramu's share of the payment is (1/8) * 3600 = ₹450.

Therefore, the share of Ramu (in ₹) will be ₹450.

Top Work and Wages MCQ Objective Questions

A and B together are supposed to do 13/15 of the work and B and C together 11/20 of the work. If the difference between wages of A and C is Rs. 7600, then the total wages of A and C is:

  1. Rs. 14000
  2. Rs. 36000
  3. Rs. 18000
  4. Rs. 56000

Answer (Detailed Solution Below)

Option 1 : Rs. 14000

Work and Wages Question 6 Detailed Solution

Download Solution PDF

Given:

Difference between wages of A and C = Rs. 7600

Formula Used:

Share in wages = Work done/Total work × Total wages

Calculation:

Let total work be 60 unit,

Work done by A and B = 13/15 × 60 = 52 unit

⇒ Work done by C = 60 – 52 = 8 unit

Work done by B and C = 11/20 × 60 = 33 unit

⇒ Work done by A = 60 – 33 = 27 unit

Work done by B = 60 – 27 – 8 = 25 unit

According to the question,

27 – 8 = 19 unit = 7600

⇒ 1 unit = 400

Total wages of A and C = (27 + 8) = 35 units = 35 × 400 = Rs. 14000

In a camp, there is a meal for 120 men or 200 children. If 150 children have taken the meal, how many men will be catered-to with remaining meal?

  1. 20
  2. 30
  3. 40
  4. 50

Answer (Detailed Solution Below)

Option 2 : 30

Work and Wages Question 7 Detailed Solution

Download Solution PDF

Given:

In a camp there is a meal for 120 men or 200 children.

Calculation:

According to the question, 150 children have taken the meal

So, 50 children left

⇒ 200 children = 120 men

⇒ 50 = 120 × (\(\frac{50}{200}\)) men

⇒ 30 men

∴ 30men will be catered-to with remaining meal.

5 women and 9 girls earn a total of ₹18,720 in 9 days, while 9 women and 16 girls earn a total of ₹ 52,080 in 14 days. How much will 12 women and 7 girls together earn (in ₹) in 13 days?

  1. 42510
  2. 41990
  3. 42380
  4. 42120

Answer (Detailed Solution Below)

Option 4 : 42120

Work and Wages Question 8 Detailed Solution

Download Solution PDF

Given:

5 women and 9 girls can earn Rs.18,720 in 9 days

9 women and 16 girls earn a total of ₹ 52,080 in 14 days

Concept:

Total work = number of workers doing work × time taken to complete the work.

Calculation:

(5W + 9G) × 9 = 18,720

(5W + 9G) = 2080 ----(i)

(9W + 16G) × 14 = 52080

(9W + 16G= 3720 ----(ii)

solving equations (i) and (ii)

⇒ 45W + 81G = 18720 ---- (iii)

⇒ 45W + 80G = 18600 ---- (iv)

by subtraction equations (iii) and (iv)

⇒ 1G = Rs. 120 

Putting the value of G in equation (i)

⇒ 5W + 1080 = 2080

⇒ 5W = 1000

⇒ W = Rs.200

According to the question:

Money earned by 12 women and 7 girls in 13days

⇒ (12 × 200 + 7 × 120) × 13

⇒ (2400 + 840) × 13

⇒ 3240 × 13 = 42120

∴ The required value is 42120.

A firm reduced employees in the ratio 12 ∶ 5 in time of inflation, and the average wage per employee increased in the ratio 9 ∶ 17. By doing so, the firm saved Rs.46,000. What was the initial expenditure (in Rs) of the firm?

  1. Rs 1,90,000
  2. Rs 90,000
  3. Rs 2,16,000
  4. Rs 2,50,000

Answer (Detailed Solution Below)

Option 3 : Rs 2,16,000

Work and Wages Question 9 Detailed Solution

Download Solution PDF

Formula Used:

Expenditure = number of employee × average wage

Calculation:

Let the number of employee of the firm be 12x and 5x pre and post reduction respectively.

and average salary be 9y and 17 y pre and post reduction respectively.

Expenditure before reduction is 12x × 9y

Expenditure after reduction is 5x × 17y

ATQ: 12x × 9y - 5x × 17y = 46000

⇒ (108 - 85)xy = 46000

⇒ 23xy = 46000

⇒ xy = 2000

Expenditure before reduction is 12x × 9y = 108 × xy = 108 × 2000 = 216000

Expenditure before reduction is Rs. 216000.

4 men and 6 women get Rs. 1600/- by doing a piece of work in 5 days, 3 men and 7 women get Rs. 1740/- by doing the same work in 6 days. In how many days 7 men and 6 women can complete the same work getting Rs. 3760/-

  1. 6 days
  2. days
  3. 10 days
  4. None of these

Answer (Detailed Solution Below)

Option 2 : 8 days

Work and Wages Question 10 Detailed Solution

Download Solution PDF

Given:

4 men and 6 women get Rs. 1600/- by doing a piece of work in 5 days

3 men and 7 women get Rs. 1740/- by doing the same work in 6 days

 7 men and 6 women can complete the same work getting Rs. 3760/-

Calculation:

Let,

M as the rate at which one man can complete the work (in Rs./day)

W as the rate at which one woman can complete the work (in Rs./day)

From the given problem, we have two equations:

4M + 6W = 1600/5          ------- (equation 1)

3M + 7W = 1740/6          ------- (equation 2)

First, multiply equation (1) by 3 and equation (2) by 4:

12M + 18W = 960           ------- (equation 3)

12M + 28W = 1160         ------- (equation 4)

Equation (4) - Equation (3)

10W = 200

W = 200 / 10 = Rs. 20/day

Substitute W into equation (1):

4M + 6 × 20 = 320

⇒ M = 200 / 4 = Rs. 50/day

Now,

Work = Rate ×  Time

3760 = (7M + 6W) × Time

3760 = (7 × 50 + 6 × 20) × Time

3760 = (350 + 120) × Time

3760 = 470 × Time

Time = 3760 / 470 = 8 days

∴ Required number of days = 3760/470 = 8 days.

Shortcut Trick
Calculation:

⇒ \((M_1 ~+~W_1)× D_1\over (Income)_1\) = \((M_2 ~+ ~W_2) D_2\over (Income)_2\)

⇒ \((4m +6w)× 5\over 1600\) = \((3m + 7w)× 6\over 1740\)

⇒ \(4m +6w\over 3m + 7w\) = \(1600×6\over 1740×5 \)

⇒ 20 m = 50 w

⇒ m : w = 5 : 2  

Now, put the respective ratio in the equation:

⇒ \((4m +6w)× 5\over 1600\) = [(4 × 5 + 6 × 2) × 5]/1600 = 1/10 

According to the question:

⇒ \((7m + 6w)× 6\over 1740\) = [(7 × 5 + 6 × 2)× d]/3760 

⇒ 1/10 = d/80

Required number of days = 80/10 = 8 days

∴ The correct answer is 8 days.

15 persons have taken a job of digging a pond in 20 days. 5 persons have left after 10 days. Again after 5 days 5 more have left. How many days would be required to complete the job?

  1. 55
  2. 25
  3. 35
  4. 45

Answer (Detailed Solution Below)

Option 3 : 35

Work and Wages Question 11 Detailed Solution

Download Solution PDF

GIVEN:

Time taken by 15 people to dig the pond = 20 days

FORMULA USED:

Man – day formula

(m1 × d1 × h1)/w1 = (m2 × d2 × h2)/w2

Where m1, m2 is number of persons working

d1, d2 is number of days taken

h1, h2 is number of hours

w1, w2 is the units of work done

CALCULATION:

15 persons have taken a job of digging a pond in 20 days

Total work = 15 × 20 = 300 units

Work done by 15 men in 10 days = 15 × 10 = 150 units

Now,

5 men left the work

Work done by 10 men in 5 days = 10 × 5 = 50 units

Again 5 men left the work

Remaining work = 300 – (150 + 50) = 100 units

⇒ Remaining work will be done in 100/5 = 20 days

∴ Total number of days taken to complete the work = 10 + 5 + 20 = 35 days

A and B undertake to do a job for Rs. 6,000. A can do it in 10 days and B can do it in 12 days. With the assistance of C, they finish the work in 4 days. How much should C be paid for his work?

  1. Rs. 2,400
  2. Rs. 1,500
  3. Rs. 1,400
  4. Rs. 1,600

Answer (Detailed Solution Below)

Option 4 : Rs. 1,600

Work and Wages Question 12 Detailed Solution

Download Solution PDF

Given:-

A can do a work in 10 days

B can do a work in 12 days

they undertake to do job for Rs. 6000

Concept used:-

Efficiancy concept related to work and time.

Total work = LCM(Time taken by all individual)

Calculation:-

Total work = LCM(10, 12)

Total work = 60 units

Rs. per unit = 6000/60 = 100 Rs. per unit

∴ A's per day work = 60/10 = 6 units

A's per day income = 6 × 100 = Rs. 600

B's per day work = 60/12 = 5 units

B's per day income = 5 × 100 = Rs. 500

Let C's per day work = x units

According to Question-

⇒ (6 × 4) + (5 × 4) + (x × 4) = 60

⇒ 24 + 20 + 4x = 60

⇒ 4x = 60 - 44

⇒ x = 16/4

⇒ x = 4 units

C's per day income = 4 × 100 = Rs. 400 

C should be paid for work = 400 × 4 = Rs.1600

A can do a piece of work in 20 days while B can do it in 30 days. They work together for 10 days and the rest of the work is done by C in 5 days. If they get Rs 560 for the whole work, how much money will A get?

  1. Rs. 160
  2. Rs. 280
  3. Rs. 200
  4. Rs. 320

Answer (Detailed Solution Below)

Option 2 : Rs. 280

Work and Wages Question 13 Detailed Solution

Download Solution PDF

Given:

Time is taken by A to do the work = 20 days

Time is taken by B to do the work = 30 days

Total wage = Rs. 560

Formula used:

Time = Total work/Efficiency

Concept used:

Wage is divided the same as efficiency and inversely proportional to the time taken

Calculation:

Work done by A in 1 day is = 1/20

Work done by B in 1 day is = 1/30

Work done by A and B together in 1 day is = (1/20 + 1/30) = 1/12

Work is done by A and B together in 10 days is = 10/12

Remaining work = 1 – 10/12 = 2/12 = 1/6

C do 1/6 of the work in 5 days

Total work done by C alone in 5 × 6 is = 30 days

Wages ratio of A, B and C = 1/20 × 10 : 1/30 × 10 : 1/30 × 5 = 6 : 4 : 2

Money A will get = 6/12 × 560 = 280

Share of money A will get is Rs 280

 Shortcut Trick

Since A can do that piece of work in 20 days and has worked for 10 days

i.e. A has done half of total work.

So A will get half of the amount paid to all i.e. = 560/2 = Rs. 280

Confusion Points

You may think that 240 is the correct answer but it is not.

It is so because the time for which C has worked is 5 days whereas A and B have worked for 10 days

Thus, Wages ratio of A, B and C = 1/20 × 10 : 1/30 × 10 : 1/30 × 5 = 6 : 4 : 2

If 15 boys earn Rs. 750 in 5 days, then how much money 25 boys will earn in 6 days?

  1. Rs. 960
  2. Rs. 1500
  3. Rs. 1200
  4. Rs. 900

Answer (Detailed Solution Below)

Option 2 : Rs. 1500

Work and Wages Question 14 Detailed Solution

Download Solution PDF

Given:-

15 boys for 5 days = at Rs 750

Calculation:-

Let 25 boys earn Rs. x in 6 days,

then according to question,

⇒ (15 × 5)/750 = (25 × 6)/x

⇒ x = 150 × 10

⇒ x = 1500

25 boys will earn Rs. 1500 in 6 days

Samir and Puneet can complete the same work in 10 days and 15 days respectively. The work was assigned for Rs.4500. After working together for 3 days Samir and Puneet involved Ashok. The work was completed in total 5 days. What amount (in Rs.) was paid to Ashok?

  1. 1500
  2. 800
  3. 750
  4. 1071

Answer (Detailed Solution Below)

Option 3 : 750

Work and Wages Question 15 Detailed Solution

Download Solution PDF

Given:

Samir's 1 day's work = 1/10

Puneet's 1 day's work = 1/15

Calculation:

(Samir + Puneet)'s 1 day's work = 1/10 + 1/15 = 1/6

(Samir + Puneet)'s 3 days work = 3 × 1/6 = 1/2

Remaining work after 3 days = 1 - 1/2 = 1/2

Remaining work completed in 2 days.

(Samir + Puneet + Ashok)'s 1 day's work = 1/2 × 1/2 = 1/4

Ashok's 1 day's work = 1/4 - 1/6 = 1/12

Ratio of work done = 5/10 : 5/15 : 2/12

= 1/2 : 1/3 : 1/6

= 3 : 2 : 1

∴ Ashok's share = 1/6 × 4500 = Rs.750

Alternate Method Samir and Puneet can complete the same work in 10 days and 15 days respectively

Total work = LCM(10, 15) = 30 units 

Efficiency of Samir = 30/10 = 3 units

Efficiency of Puneet = 30/15 = 2 units 

According to the question,

Samir and Puneet worked for (3 + 2) = 5 days 

Work done by Samir and Puneet in 5 days = 5 × 5 = 25 units 

Remaining 5 units of work is done by Ashok in 2 days

Efficiency of Ashok = 5/2 = 2.5 units 

Total amount = Rs. 4500

Amount given for 1 unit of work = 4500/30 = 150

Amount given to Ashok = 150 × 5 = Rs. 750

Get Free Access Now
Hot Links: teen patti real money app teen patti - 3patti cards game downloadable content teen patti customer care number teen patti flush teen patti real cash game