Download Solution PDFPlant capacity factor is the:
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFPlant capacity factor (P.C.F.): It is the ratio of actual energy produced to the maximum possible energy that could have been produced during a given period.
P.C.F.
P.C.F.
The plant capacity factor is also known as the ratio of average demand to plant capacity.
The plant capacity factor is an indication of the reverse capacity of the plant. A power station is so designed that it has some reserve capacity for meeting the increased load demand in the future. Therefore, the installed capacity of the plant is always somewhat greater than the maximum demand on the plant.
Reserve capacity = Plant capacity – Maximum demand
If the maximum demand on the plant is equal to plant capacity, then load factor and plant capacity factor will have the same value. In such a case, the plant will have no reserve capacity.
Plant use factor: It is the ratio of kWh generated to the product of plant capacity and the number of hours for which the plant was in operation.
Load factor: The ratio of average load to the maximum demand during a given period is known as the load factor.
Load factor = Average load / Maximum demand
Capacity factor = Load factor × plant use factor
Last updated on Jul 1, 2025
-> SSC JE Electrical 2025 Notification is released on June 30 for the post of Junior Engineer Electrical, Civil & Mechanical.
-> There are a total 1340 No of vacancies have been announced. Categtory wise vacancy distribution will be announced later.
-> Applicants can fill out the SSC JE application form 2025 for Electrical Engineering from June 30 to July 21.
-> SSC JE EE 2025 paper 1 exam will be conducted from October 27 to 31.
-> Candidates with a degree/diploma in engineering are eligible for this post.
-> The selection process includes Paper I and Paper II online exams, followed by document verification.
-> Prepare for the exam using SSC JE EE Previous Year Papers.