Floods and River Training MCQ Quiz - Objective Question with Answer for Floods and River Training - Download Free PDF

Last updated on Mar 29, 2025

Latest Floods and River Training MCQ Objective Questions

Floods and River Training Question 1:

As per CWC guidelines to select floods, aqueducts are recommended for a design flood for a time period of:

  1. 30 years
  2. 100 years
  3. 50 years
  4. 75 years

Answer (Detailed Solution Below)

Option 3 : 50 years

Floods and River Training Question 1 Detailed Solution

Explanation:

CWC Guidelines for Aqueducts Design Flood Period

As per the Central Water Commission (CWC) guidelines, the design flood for aqueducts should be selected based on a specified time period. The design flood is a critical parameter in ensuring the structural integrity and safety of aqueducts during flood events.

As per CWC guidelines to select floods:

(a) For spillways for major and medium projects with storage more than 60 Mm³ recommended design flood is either probable maximum flood or flood frequency method with return period of 1000 years.

(b) For permanent barrages and minor dams with capacity less than 60 Mm³ recommended design flood is standard probable flood (or) flood with time period of 100 years whichever is higher.

(c) Aqueducts is recommended for a design flood for time period of 50 years.

Floods and River Training Question 2:

Study the following statements:

(i) Levees are constructed parallel to the river flow.

(ii) Spurs are constructed parallel to the river flow.

(iii) Levees are constructed transverse to the river flow.

(iv) Spurs are constructed transverse to the river flow.

The correct answer is:

  1. (iii) and (iv)
  2. (iv) and (i)
  3. (i) and (ii)
  4. (ii) and (iii)
  5. None of the above

Answer (Detailed Solution Below)

Option 2 : (iv) and (i)

Floods and River Training Question 2 Detailed Solution

Concept:

Levees

Levees construction is a method of river training. They are constructed to protect the riverbanks from flooding. It is basically an embankment constructed along the river so that water remains contained in between the levees during flooding.

Effects of levees construction:

  • It reduces the width of the river stream, so flow velocity is increased.
  • It contains the flood water in between the levees only, which increases the discharge.
  • It increases the water surface elevation during flooding.
  • It decreases the flood storage as maximum flood water becomes the part of discharge.

Groynes / Spurs: 

  • These are the embankment type structures constructed transverse to the river flow.
  • They extend into the river from the bank and may also be called transverse dykes.
  • They are constructed to protect the bank by deflecting the current away from the bank.
  • They train the river to flow along a desired course by attracting, deflecting or repelling the flow.

Floods and River Training Question 3:

Among the following methods of flood control, identify a non-structural measure of flood control. 

  1. Flood plain zoning 
  2. Detention reservoirs 
  3. Channel improvement 
  4. Levees 

Answer (Detailed Solution Below)

Option 1 : Flood plain zoning 

Floods and River Training Question 3 Detailed Solution

Explanation:

  • Flood Plain Zoning (Non-Structural Measure)

    • This involves land-use planning to restrict construction in flood-prone areas.
    • It is a policy-based approach, not a physical structure.
  • Detention Reservoirs (Structural Measure)

    • These are artificial reservoirs designed to temporarily store excess floodwater.
    • Since it involves physical construction, it is a structural measure.
  • Channel Improvement (Structural Measure)

    • Modifying or enlarging river channels to improve water flow and reduce flooding.
    • It involves physical construction, making it a structural measure.
  • Levees (Structural Measure)

    • Embankments built along rivers to prevent floodwaters from spilling over.
    • It is a physical flood barrier, making it a structural measure.

Floods and River Training Question 4:

A river training work is generally required when the river is

  1. aggrading type
  2. degrading type
  3. meandering type
  4. both aggrading type and degrading type

Answer (Detailed Solution Below)

Option 3 : meandering type

Floods and River Training Question 4 Detailed Solution

Explanation:

River Training Works

River training works are constructed for several reasons but the fundamental objective is to restrict the horizontal movement of the river channel along a certain alignment.

The measures are adopted to train the river because rivers in alluvial flood plains are prone to meandering and hence cause a lot of damage to life and property.

Additional InformationMeandering

  • Meandering is considered a wave phenomenon.
  • A meander is formed when moving water in a stream erodes the outer banks and widens its valley and the inner part of the river has less energy and deposits what it is carrying.
  • A meandering channel tends to be deeper towards the concave bank and progressively gets shallower towards the convex bank.

F1 Killi 24.11.20 Pallavi D2

Floods and River Training Question 5:

A mass curve for typical stream is shown for 

  1. 6-year period
  2. 5-year period
  3. 4-year period
  4. 3-year period

Answer (Detailed Solution Below)

Option 1 : 6-year period

Floods and River Training Question 5 Detailed Solution

Explanation:

A mass curve for a typical stream is usually shown for a 6-year period. This is because the 6-year period is a common period for hydrological analysis. It is long enough to capture the variability of the streamflow, but it is not so long that the data becomes too difficult to manage.

Top Floods and River Training MCQ Objective Questions

Temporary spurs are also called:

  1. Weirs
  2. Canals
  3. Bunds
  4. Barrages

Answer (Detailed Solution Below)

Option 3 : Bunds

Floods and River Training Question 6 Detailed Solution

Download Solution PDF

Temporary spurs or bunds are temporary structures constructed every year after floods. A bund is a structure made to project flow from a riverbank into a stream or river with the aim of deflecting the flow away from the side of the river on which the groyne is built.

Important Points:

Bunds are temporary in nature whereas Weirs and barrages are permanent in nature.

In a weir, the water overflows the weir, but in a dam, the water overflows through a special place called a spillway. Weirs have traditionally been used to create mill ponds.

A barrage is a weir that has adjustable gates installed over top of it, to allow different water surface heights at different times.

Sarda type fall was designed to:

  1. Minimise the depth of cutting
  2. Maximise the depth of cutting
  3. Maintain the depth of cutting
  4. Have no relation with depth of cutting

Answer (Detailed Solution Below)

Option 1 : Minimise the depth of cutting

Floods and River Training Question 7 Detailed Solution

Download Solution PDF

Explanation:

Falls and drops are made when the natural ground is steeper than bed slope of channel.

Types of falls:-

1. Ogee falls

2. Rapids

3. Trapezoidal notch falls

4. Syphon well drops

5. Sarda type falls or simple verticle drop

6. Straight glacis falls

7. Montague type falls

8. Inglis falls or Baffle falls

Ordinary falls results in the deep cutting of bed strata as the water hits the bed surface.

Sarda type fall is the combination of small-sized falls resulting in gradual energy dissipation of the water without hydraulic jump formation. Such combination is adopted for weaker strata as the depth of cutting is minimized. It is also economical to build to sarda type fall.

Among the following river training works, which are aligned either perpendicular or at an angle to the banks, identify the one having a difference in alignment when compared to others.

  1. Groynes
  2. Guide banks
  3. Levees
  4. Flood walls

Answer (Detailed Solution Below)

Option 1 : Groynes

Floods and River Training Question 8 Detailed Solution

Download Solution PDF

Concept:

Groynes or Spurs:

  • A groyne is a rigid hydraulic structure built either from the shore (in case of seas) or bank (in case of rivers) in order to dissipate the wave energy or to protect the banks from erosion by trapping the sediments.
  • They are perpendicular or slightly oblique to the shoreline.

Guide banks:

  • Guide banks are meant for guiding and confining the flow in a reasonable waterway at the site of the structure.
  • The design of the guide banks is based on the theory developed by Mr. Bells. Hence, guide banks are also known as Bell’s bunds.
  • The guide banks are constructed parallel or approximately parallel to the direction of flow. They extend both upstream and downstream of the abutments of the hydraulic structure.
  • The guide banks may be provided on either side of the hydraulic structure or on one side as required.

Levees:

  • It is a low ridge or earthen embankment built along the edges of a stream or river channel to prevent flooding of the adjacent land. 
  • Levees are usually embankments of dirt built wide enough so that they will not collapse or be eroded when saturated with moisture from rivers running at unusually high levels.

Flood walls:

  • When no space is available for the construction of a levee or when it is not suitable to construct the levee due to local site conditions, then a flood wall is constructed as local flood hazard prevention for some important area situated at a low level.
  • There are masonry or concrete walls constructed just on the river bank.

Study the following statements:

(i) Levees are constructed parallel to the river flow.

(ii) Spurs are constructed parallel to the river flow.

(iii) Levees are constructed transverse to the river flow.

(iv) Spurs are constructed transverse to the river flow.

The correct answer is:

  1. (iii) and (iv)
  2. (iv) and (i)
  3. (i) and (ii)
  4. (ii) and (iii)

Answer (Detailed Solution Below)

Option 2 : (iv) and (i)

Floods and River Training Question 9 Detailed Solution

Download Solution PDF

Concept:

Levees

Levees construction is a method of river training. They are constructed to protect the riverbanks from flooding. It is basically an embankment constructed along the river so that water remains contained in between the levees during flooding.

Effects of levees construction:

  • It reduces the width of the river stream, so flow velocity is increased.
  • It contains the flood water in between the levees only, which increases the discharge.
  • It increases the water surface elevation during flooding.
  • It decreases the flood storage as maximum flood water becomes the part of discharge.

Groynes / Spurs: 

  • These are the embankment type structures constructed transverse to the river flow.
  • They extend into the river from the bank and may also be called transverse dykes.
  • They are constructed to protect the bank by deflecting the current away from the bank.
  • They train the river to flow along a desired course by attracting, deflecting or repelling the flow.

Guide banks are provided in rivers to:

  1. increase the depth of flow in the river
  2. decrease the velocity of flow of the river
  3. channelise the flow of the river
  4. reduce the flood peak

Answer (Detailed Solution Below)

Option 3 : channelise the flow of the river

Floods and River Training Question 10 Detailed Solution

Download Solution PDF

Explanation:

Guide banks are meant for guiding and confining the flow in a reasonable waterway at the site of the structure i.e., channelize the flow of the river

F1 Ankita 13-02-21 Savita D2

Guide Banks or Bell’s Bunds:

  • Rivers in flood plains submerge very large areas during flood periods.
  • Naturally, when some structure is to be constructed across such a river (for example, bridge, weir, etc.), it is very expensive to construct the work spanning the whole width of the river.
  • To economies, some training work may be constructed to confine the flow of water within a reasonable waterway. 

Meandering of a river is due to 

  1. Sediment load of streams
  2. Discharge and hydraulic properties of streams
  3. Erodibility of the bed and banks of stream
  4. The natural topography of the location

Answer (Detailed Solution Below)

Option 3 : Erodibility of the bed and banks of stream

Floods and River Training Question 11 Detailed Solution

Download Solution PDF

Concept:

Meandering River:

  • The formation of successive bends of reverse order may lead to the formation of a complete S curve called Meanders.
  • When consecutive curves of reverse order connected with short straight reaches called crossings are developed in a river reach, the river is stated to be a Meandering river.

Meandering of a river is due to erodibility of the bed and banks of streams.

Causes:

1. Extra turbulence generated by excess of river sediment during floods. When the silt charge is in excess of the quantity required for stability, the river starts building up its slope by depositing the silt on its bed.

2. The increase in bed slope tends to increase the width of channel, if the banks are not resistant. The banks are attacked by river water and in the process one bank is likely to be attacked slightly more than the other, causing a slight deviation in flow. This slight deviation from the uniform axial flow, helps in improving more and more flow towards one bank than towards the other. This process continues causing once bank convex and another concave. Hence, increasing slope is also a reason for meandering.

F1 N.M Madhu 15.04.20 D 5

Important Points

Meander parameters:

Meander Length: It is the axial length of one mender, i.e. tangential distance between the corresponding points of meander.

Meander Belt: It is the distance between the outer edges of clockwise and anticlockwise loops.

Meander Ratio: It is the ratio of meander belt to meander length.

Tortuosity: It is the ratio of length along the channel (actual length) to the direct axial length.

Crossings or cross-over: It is the shortest reaches of the river, connecting two consecutive clockwise and anticlockwise loops.

The spacing between adjacent spurs in river training work is generally kept between ______ times the spur length.

  1. 1.5 to 2.5
  2. 1 to 2
  3.  2 to 2.5
  4. 2.5 to 3.5

Answer (Detailed Solution Below)

Option 3 :  2 to 2.5

Floods and River Training Question 12 Detailed Solution

Download Solution PDF

Concept:

Groynes or spurs: 

  • These are constructed transverse to the river flow extending from the bank into the river.
  • This form of river training works perform one or more functions such as training the river along the desired course to reduce the concentration of flow at the point of attack, creating a slack flow for silting up the area in the vicinity and protecting the bank by keeping the flow away from it.
  • Each groyne can protect only a certain length and so the primary factor governing the spacing between adjacent groynes is their lengths. Generally, a spacing of 2 to 2.5 times the length of groynes at convex banks and equal to the length at concave banks is adopted.


Additional Information

Groynes or spurs are classified as -

  1.  Permeable or impermeable
  2.  Submerged or non-submerged
  3.  Attracting, deflecting repelling and sedimenting and
  4. T-shaped (Denehey), hockey (or Burma) type, kinked type, etc. 

A flood of certain magnitude has a return period of 25 years. The probability of exceedance is

  1. 4%
  2. 12%
  3. 16%
  4. 32%

Answer (Detailed Solution Below)

Option 1 : 4%

Floods and River Training Question 13 Detailed Solution

Download Solution PDF

The probability of exceedance means that probability that flood of certain magnitude will be equalled or exceeded in a particular year during its entire design life.

Probability of exceedance, \(P = \frac{1}{T};\) where T is return period

\({\rm{P}} = \frac{1}{{25}} = 0.04{\rm{\;or\;}}4{\rm{\% }}\)

The probability of exceedance is 4 percent.

If D is the depth of scour below original bed, then the width of launching apron is generally taken as

  1. 1.2 D
  2. 1.5 D
  3. 2.0 D
  4. 2.5 D

Answer (Detailed Solution Below)

Option 2 : 1.5 D

Floods and River Training Question 14 Detailed Solution

Download Solution PDF

Explanation

Launching Apron:

  • To protect the face of the guide bank at the river bed level a thick stone cover is laid on the bed. It is called an apron. When the scour undermines the river bed the apron comes down or launches to cover the face of the scour. Hence it is called Launching apron also.
  • Heavy scour of the river bed at curved heads and shanks of guide banks can cause undermining of stone pitching thereby resulting in failure of guide banks. Such a failure can be prevented by providing a launching apron beyond the toe of guide banks.
  • The width of the launching apron is generally taken as 1.5D.

F1 Madhuri Engineering 26.08.2022 D1

A silt control device consisting of a number of rectangular tunnels - provided parallel to the axis of head regulator and terminating near the under sluiced weir - to allow the clearer water to flow through the head regulator is called:

  1. silt excluder
  2. silt tunnel
  3. under sluice
  4. silt ejector

Answer (Detailed Solution Below)

Option 1 : silt excluder

Floods and River Training Question 15 Detailed Solution

Download Solution PDF

Concept:

Silt regulation works are required to preformed to control the erosion along the banks.

Two popular silt regulation works are as silt excluders and ejectors.

Silt excluders silt control device consisting of a number of rectangular tunnels - provided parallel to the axis of head regulator and terminating near the under sluiced weir - to allow the clearer water to flow through the head regulator. Silt excluders are constructed on the bed of the river, upstream of the head regulator.

Silt ejectors also called silt extractors, and it extracts the silt from the canal water after the silted water has travelled a certain distance in the off-take canal. Silt ejectors are constructed on the bed of the canal and a little distance downstream from the head regulator.

These works are, therefore, constructed on the bed of the canal, and little distance downstream from the head regulator.

F1 N.M Madhu 02.04.20 D1

 

F1 N.M Madhu 02.04.20 D2

Get Free Access Now
Hot Links: teen patti go yono teen patti teen patti wink teen patti lucky