Download Solution PDFWhich of the following statement is NOT correct about PERT ?
Answer (Detailed Solution Below)
Option 2 : In a PERT chart, ‘Nodes’ represent the activities or tasks and ‘Arrows’ represent events or milestones in the project.
Detailed Solution
Download Solution PDFThe correct answer is - Option 2
Key Points
- Option 2 is incorrect because in a PERT chart, ‘Nodes’ represent events or milestones, and ‘Arrows’ represent the activities or tasks.
- Nodes (also called events) signify the start or end points of tasks.
- Arrows (also called activities) depict the actual tasks or operations that move the project from one event to another.
Additional Information
- PERT (Program Evaluation and Review Technique)
- Developed primarily for planning and scheduling large and complex projects.
- Introduced by the United States Navy in the late 1950s.
- It helps in identifying the critical path and potential delays in the project timeline.
- Time Estimates in PERT
- PERT utilizes three-time estimates to account for uncertainty:
- Optimistic Time (O): The minimum possible time required to accomplish a task.
- Most Likely Time (M): The best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
- Pessimistic Time (P): The maximum possible time required to accomplish a task, assuming everything goes wrong.
- These estimates help in calculating the expected time for each activity.
- PERT utilizes three-time estimates to account for uncertainty:
- History of PERT
- PERT was developed during the period between 1950-1960.
- It was used in the Polaris missile project by the United States Navy.
- PERT has since been adopted in various industries for project management.