Download Solution PDFThe most important consideration when making a detailed estimate is:
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFThe correct answer is option 2.
Factors to be considered During Preparation of Detailed Estimate:
1.) The nature of work:
- If nature of work is large then transportation charges, availability of material and labour should be kept mind.
- If nature of work is small then use of local materials and labour available should be done.
2.) Quantity and availability of material:
- If quantity of material required is in large amount then concept of bulk purchasing in whole sale should be used, while deciding rates of items.
3.) Transportation of materials:
- If material required for project is not available locally the transportation charges should be added to each item while preparing detailed estimate.
4.) Location of site:
- If site is in the remote area or away from city then transportation charge should be included while costing.
- If site is not approachable then cutting of jungles construction of pilot roads, arrangement of electricity, transfer of machinery etc. requires large cost.
5.) Local labour charges:
- For preparing detailed estimate, local labour charges should be known to estimator.
- These charges should be revised from time to time.
Last updated on Jun 16, 2025
-> SSC JE Electrical 2025 Notification will be released on June 30 for the post of Junior Engineer Electrical/ Electrical & Mechanical.
-> Applicants can fill out the SSC JE application form 2025 for Electrical Engineering from June 30 to July 21.
-> SSC JE EE 2025 paper 1 exam will be conducted from October 27 to 31.
-> Candidates with a degree/diploma in engineering are eligible for this post.
-> The selection process includes Paper I and Paper II online exams, followed by document verification.
-> Prepare for the exam using SSC JE EE Previous Year Papers.