The following units are included in a sewage treatment plant.

1. Screening

2. Grit removal

3. Secondary sedimentation

4. Aeration

5. Primary sedimentation

The correct sequence of these units is:

This question was previously asked in
OSSC JE Civil Mains (Re-Exam) Official Paper: (Held On: 3rd Sept 2023)
View all OSSC JE Papers >
  1. 1, 2, 3, 4, 5
  2. 1, 2, 5, 4, 3
  3. 2, 1, 4, 5, 3
  4. 2, 1, 4, 3, 5

Answer (Detailed Solution Below)

Option 2 : 1, 2, 5, 4, 3
Free
OSSC JE Civil Geo-technical Engineering Mock Test
0.7 K Users
20 Questions 40 Marks 36 Mins

Detailed Solution

Download Solution PDF

Explanation:

Sewage treatment plants consists of the following procedures:

1. Screening

  • These are placed before grit chambers so as to trap and remove floating matter, such as pieces of cloth, paper, wood cork, hair, fiber, kitchen refuse, fecal solids, etc in the sewage.
  • Those floating material if not removed will choke the pipes or adversely affect the working of the pumps.

2. Grit removal basins

  • Grit chambers or detritus tanks are the sedimentation basins placed in front of the wastewater treatment plant to remove inorganic particles such as sand, gravel, grits, shells, bones, and other non-putrescible material.
  • They are usually placed after the fine screens to remove particles of size up to 0.2 mm or so.

3. Primary sedimentation

  • The primary sedimentation tanks are thus designed to remove a part of the organic matter from the sewage effluent coming from the grit chambers.
  • These are designed for effecting the settlement of particles by reducing the flow velocity or by detaining the sewage in them.

4. Aeration

  • From the primary sedimentation tank, the sewage flows to the aeration tank and is mixed with activated sludge.
  • These are rectangular tanks in which air is continuously introduced into these tanks.

5. Secondary sedimentation

  • From the aeration tank, the sewage flows to the final secondary sedimentation tank.
  • The secondary sedimentation tank removes bioflocculated solids.
  • The produce an effluent sufficiently classified to meet discharge standards and must concentrate the biological solids to minimize the quantity of sludge to handle.
Latest OSSC JE Updates

Last updated on Jun 4, 2025

-> OSSC JE Preliminary Fiinal Answer Key 2025 has been released. Applicants can raise objections in OSSC JE answer key till 06 June 2025.

-> OSSC JE prelim Exam 2025 was held on 18th May 2025.(Advt. No. 1233/OSSC ).

-> The OSSC JE 2024 Notification was released for 759 vacancies through OSSC CTSRE 2024.

-> The selection is based on the written test. This is an excellent opportunity for candidates who want to get a job in the Engineering sector in the state of Odisha.

-> Candidates must refer to the OSSC JE Previous Year Papers to understand the type of questions in the examination. 

Get Free Access Now
Hot Links: teen patti game - 3patti poker teen patti bliss teen patti master downloadable content teen patti royal - 3 patti