Dummy activity:
- While establishing the relationships and drawing the network diagram sometimes it so happens that there does not exist any real activity between two events but an event cannot be said to have occurred unless and until some other event has occurred. Such cases are shown on the network diagram as dummy activities.
- The purpose of dummy activity is to maintain the logic of a network diagram.
- Since no real activity takes place between two such events, the dummy activity does not consume any resources.
- It also does not consume time duration.
- Dummy activities are used only in case of absolute necessity.
- The symbolic representation of dummy activity is shown as-
Here, the dummy activity is between 2 - 3 which is given by dotted lines.
Last updated on May 26, 2025
-> UPPSC AE result 2025 has been released for Prelims exam.
-> UPPSC AE Answer Key 2025 has been uploaded on 23rd April 2025.
-> UPPSC AE Exam was conducted 20th April 2025 on its official website.
-> The UPPSC AE Exam Date 2025 has been released.
-> The Prelims & Mains exam will be conducted on 20th April & 28th September 2025 respectively.
-> A total of 604 vacancies have been released.
-> The applications must be submitted online between 17th December 2024 to 17th January 2025.
-> The selection process includes a written exam, interview, and document verification.
-> Candidates with a BE/B.Tech degree in the relevant discipline, between 21 to 40 years of age are eligible for this post.