Download Solution PDFA can complete \(1 \over 3\) of a work in 7 days and B can complete \(2 \over 7\) of the same work in 10 days. In how many days can both A and B together complete the work?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFGiven:
A can complete a work = 7 × 3 = 21 days
B can complete a work = 10 × (7/2) = 35 days
Formula used:
Total work = efficiency × time
Calculation:
Efficiency | Person | Time | Total work |
5 | A | 21 | 105 |
3 | B | 35 |
Now,
Time taken by A and B together to complete the work = 105/8
⇒ 13\(1\over8\) days
∴ The correct answer is 13\(1\over8\) days.
Last updated on Jun 25, 2025
-> The SSC CGL Notification 2025 has been released on 9th June 2025 on the official website at ssc.gov.in.
-> The SSC CGL exam registration process is now open and will continue till 4th July 2025, so candidates must fill out the SSC CGL Application Form 2025 before the deadline.
-> This year, the Staff Selection Commission (SSC) has announced approximately 14,582 vacancies for various Group B and C posts across government departments.
-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025.
-> Aspirants should visit ssc.gov.in 2025 regularly for updates and ensure timely submission of the CGL exam form.
-> Candidates can refer to the CGL syllabus for a better understanding of the exam structure and pattern.
-> The CGL Eligibility is a bachelor’s degree in any discipline.
-> Candidates selected through the SSC CGL exam will receive an attractive salary. Learn more about the SSC CGL Salary Structure.
-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.
-> Candidates should also use the SSC CGL previous year papers for a good revision.
->The UGC NET Exam Analysis 2025 for June 25 is out for Shift 1.