Question
Download Solution PDF4 men’s work is equal to 6 women’s work, and 4 women’s work is equal to 6 boys’ work. A boy can finish the work in 60 days. In how many days can the work be finished by a man and a woman together?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFCalculation:
According to the question,
4M = 6W
⇒ M : W = 3 : 2
Again, 4W = 6B
⇒ W : B = 3 : 2
So, M : W : B = 9 : 6 : 4
A boy can finish the work in 60 days, so total work = (60 × 4) = 240 unit
Now, a man and a woman together can do the work in 240/15 = 16 days
∴ The correct answer is 16 days
Last updated on Jul 9, 2025
-> The SSC CGL Notification 2025 for the Combined Graduate Level Examination has been officially released on the SSC's new portal – www.ssc.gov.in.
-> Bihar Police Admit Card 2025 Out at csbc.bihar.gov.in
-> This year, the Staff Selection Commission (SSC) has announced approximately 14,582 vacancies for various Group B and C posts across government departments.
-> The SSC CGL Tier 1 exam is scheduled to take place from 13th to 30th August 2025.
-> Aspirants should visit ssc.gov.in 2025 regularly for updates and ensure timely submission of the CGL exam form.
-> Candidates can refer to the CGL syllabus for a better understanding of the exam structure and pattern.
-> The CGL Eligibility is a bachelor’s degree in any discipline.
-> Candidates selected through the SSC CGL exam will receive an attractive salary. Learn more about the SSC CGL Salary Structure.
-> Attempt SSC CGL Free English Mock Test and SSC CGL Current Affairs Mock Test.
-> The AP DSC Answer Key 2025 has been released on its official website.
-> The UP ECCE Educator 2025 Notification has been released for 8800 Posts.