সময়সূচী তৈরি MCQ Quiz in বাংলা - Objective Question with Answer for Scheduling - বিনামূল্যে ডাউনলোড করুন [PDF]

Last updated on Mar 9, 2025

পাওয়া সময়সূচী তৈরি उत्तरे आणि तपशीलवार उपायांसह एकाधिक निवड प्रश्न (MCQ क्विझ). এই বিনামূল্যে ডাউনলোড করুন সময়সূচী তৈরি MCQ কুইজ পিডিএফ এবং আপনার আসন্ন পরীক্ষার জন্য প্রস্তুত করুন যেমন ব্যাঙ্কিং, এসএসসি, রেলওয়ে, ইউপিএসসি, রাজ্য পিএসসি।

Latest Scheduling MCQ Objective Questions

Top Scheduling MCQ Objective Questions

সময়সূচী তৈরি Question 1:

Data on five products to be processed on a single machine is given below.

Product

Release

time

Processing

time

Due

date

P

0

3

10

Q

2

4

9

R

0

2

15

S

1

5

11

T

1

1

13

 

For the processing sequence R-P-S-T-Q, total tardiness is ________

  1. 5
  2. 10
  3. 28
  4. 0

Answer (Detailed Solution Below)

Option 2 : 10

Scheduling Question 1 Detailed Solution

Jobs

Ti = RT + PT

Flow time

Due date

Ci - Di

R

2

2

15

-13

P

3

5

10

-5

S

6

11

11

0

T

2

13

13

0

Q

6

19

9

10

 

Positive lateness is called Tardiness

Total Tardiness = 10 days 

সময়সূচী তৈরি Question 2:

For the following set of jobs to be processed on two machines, find the value of make span time …….. minutes

Jobs

Machine 1 (in min)

Machine 2 (in min)

A

6

7

B

10

8

C

12

9

D

7

12

Answer (Detailed Solution Below) 43

Scheduling Question 2 Detailed Solution

Concept: Following are the steps:

Step 1: First find the optimal sequence using Johnson’s rule

Step 2: Draw a table showing in and out time for each job using the processing time.

Step 3: Calculate the asked values.

Calculation:

Step 1: Using Johnson’s rule the optimal sequence is A-D-C-B

Sequencing of ‘N’ Jobs on Two Machine

In this type of problem, we consider that two machines are A and B and the assumption is that the processing order is fixed. Each of the jobs numbered i = 1, 2, 3, -----, n has processing times Ai and Bi respectively. The problem is to find a processing order for different jobs and to ensure that the ideal time for both the machines is minimized. In other words, the aim is to maximize machine utilization. This is achieved by using Jhonson’s Algorithm.

Step(i): Find out the minimum of Ai and Bi. If the minimum is Ak then process the kth job in the beginning. If the minimum is Br then process the rth job in the end.

Step(ii): When a particular job is placed in a sequence strike it off.

Step(iii): If Ak = Br then in this case process the kth job first and rth job last.

If both equal values occur on machine A then select the one which has lowest value on B first. If both values occur on machine B then select the one with the lowest value on A first.  

Step 2:

Jobs

Machine 1

Machine 2

 In time

Out time

In time

Out time

A

0

6

6

13

D

6

13

13

25

C

13

25

25

34

B

25

35

35

43

 

Make span time = 43 minutes

সময়সূচী তৈরি Question 3:

In job shop scheduling, which sequence of operations typically results in optimal resource utilization and minimization of job waiting times? 

  1. First In, First Out (FIFO)  
  2. Shortest Processing Time (SPT) first  
  3. Earliest Due Date (EDD) 
  4. Longest Processing Time (LPT) first  

Answer (Detailed Solution Below)

Option 2 : Shortest Processing Time (SPT) first  

Scheduling Question 3 Detailed Solution

Explanation:

Job Shop Scheduling:

  • Job shop scheduling involves planning, allocating, and managing resources and tasks to ensure optimal utilization of resources and minimization of waiting times in a production environment.
  • This process is critical in manufacturing and service industries where multiple jobs need to be processed on various machines.
  • In job shop scheduling, jobs with different processing requirements are assigned to specific machines in a sequence that optimizes resource utilization and minimizes job waiting times.
  • The sequence in which jobs are processed can significantly impact overall efficiency and productivity.

Advantages of Optimal Scheduling:

  • Maximized resource utilization by ensuring machines and workers are continuously engaged.
  • Reduced waiting times for jobs, leading to faster turnaround and improved customer satisfaction.
  • Minimized production costs by reducing idle times and improving workflow efficiency.

Disadvantages of Suboptimal Scheduling:

  • Increased waiting times and delays, leading to missed deadlines and customer dissatisfaction.
  • Underutilization of resources, resulting in higher operational costs.
  • Increased complexity in managing and rescheduling tasks, leading to inefficiencies.

Shortest Processing Time (SPT):

  • The Shortest Processing Time (SPT) rule is a widely used heuristic in job shop scheduling because it tends to minimize the average waiting time for jobs.
  • By processing jobs with shorter durations first, the overall flow of work is smoother, and bottlenecks are reduced, leading to optimal resource utilization.

Why SPT is Optimal:

  • The Shortest Processing Time (SPT) rule works effectively because it prioritizes jobs that can be completed quickly, thereby freeing up resources faster for subsequent tasks. This approach reduces the time that jobs spend waiting to be processed, leading to a lower average waiting time and improved resource utilization.

Additional InformationFirst In, First Out (FIFO)

  • This scheduling rule processes jobs in the order they arrive, regardless of their processing times. While FIFO is simple to implement and fair in terms of job order, it does not consider the processing time of each job. This can lead to longer waiting times, especially if a job with a long processing time arrives early and blocks subsequent shorter jobs.

Earliest Due Date (EDD)

  • This rule prioritizes jobs based on their due dates, with jobs having the earliest due dates scheduled first. Although EDD can be useful in meeting deadlines, it does not necessarily optimize resource utilization or minimize waiting times. Jobs with shorter processing times might still be delayed, leading to inefficiencies.

Longest Processing Time (LPT) first

  • This rule schedules jobs with the longest processing times first. While this can sometimes help in balancing the load across machines, it often leads to increased waiting times for shorter jobs. As a result, it is generally less effective in minimizing average waiting times compared to the SPT rule.

সময়সূচী তৈরি Question 4:

A set of jobs are to be processed on a single machine using shortest processing time rule. Find the average tardiness per Job (in minutes).

Jobs

A

B

C

D

E

F

G

H

Processing Time

14

10

7

17

13

9

16

8

Due date

51

79

62

71

84

81

59

95

  1. 4.7
  2. 5.2
  3. 6.9
  4. 6.3

Answer (Detailed Solution Below)

Option 4 : 6.3

Scheduling Question 4 Detailed Solution

Applying shortest processing time rule and arranging according.

Jobs

Procesing

Time

Job flow

time

Due

date

Tardiness

C

7

7

62

0

H

8

15

95

0

F

9

24

81

0

B

10

34

79

0

E

13

47

84

0

A

14

61

51

10

G

16

77

59

18

D

17

94

71

23

                                                                                   \(= {\rm{\Sigma \;}}51\)

Average Tardiness \(= \frac{{51}}{8} = 6.375\;min\)

সময়সূচী তৈরি Question 5:

Routing is essential in the following type of industry:

  1. Assembly industry
  2. Process industry
  3. Job order industry
  4. Mass production industry

Answer (Detailed Solution Below)

Option 1 : Assembly industry

Scheduling Question 5 Detailed Solution

Explanation:

  • Routing determines what work is to be done and where and how it will be done. Taking from raw material to the finished product, routing decides the path and sequence of operations to be performed on the job from one machine to another.
  • Routing is essential in the Assembly industry

Railways Solution Improvement Satya 10 June Madhu(Dia)

A production planning and control system has many functions to perform, some before the arrival of raw materials and tools, and others while the raw material undergoes processing.

There are four steps in the process of production planning and control:

RRB JE ME 38 14Q IM Part 1 Hindi - Final nita Q7

Routing: Routing can be defined as the process of deciding the path (route) of work and the sequence of operations.

Scheduling: Scheduling function determines when an operation is to be performed, or when work is to be completed.

Dispatching: It is the action, doing or implementation stage. It comes after routing and scheduling. Dispatching means starting the process of production. It provides the necessary authority to start the work.

Expedition or follow-up: It is designed to keep track of the work effort. The aim is to ensure that what is intended and planned is being implemented. It maintains proper records of work, delays, and bottleneck. Such records can be used in the future to control production.

সময়সূচী তৈরি Question 6:

Which of the following is the correct definition of the critical ratio in scheduling

  1. Demand time/Supply lead time
  2. Supply lead time/Demand time
  3. Demand time/Manufacturing lead time
  4. Manufacturing lead time/Demand time
  5. None of the above

Answer (Detailed Solution Below)

Option 3 : Demand time/Manufacturing lead time

Scheduling Question 6 Detailed Solution

Explanation:

Scheduling:

Scheduling is done to determine the timing and order of operations to optimize the use of resources to meet production requirements.

Jobs are scheduled according to their priority there are several Priority rules existing for a job

Critical Ratio:

Critical ratio is calculated by dividing the time remaining until a job's due date by the total shop time remaining for the job.

Shop time is regarded as the setup time, processing time, and movement time and expected waiting times of all remaining operations, including the operation being scheduled.

\(Critical\;Ratio = \frac{{Demand\;Time}}{{Manufacturing\;Lead\;time}}\)

Where demand time is given by = Due date – Today’s date

If the critical ratio is less than one it means that job is behind the schedule, if the critical ratio is greater than one it shows that the job is running ahead of the schedule. The jobs with lowest critical ratio is scheduled next.

Shortest processing time rule:

That work is performed first which has shortest processing time.

Earliest due date rule:

Jobs are sequenced in increasing order of their due date.

Slack time remaining rule:

Jobs are sequenced in order of increasing slack time

Slack time = Due date – Processing Time

সময়সূচী তৈরি Question 7:

The COVID -19 cases in Hyderabad for different months is shown below from April to August. The experts forecasted the cases in the month of April as 100 with a soothing constant of 0.8.

Month

Actual cases registered in the month

April

140

May

350

June

650

July

800

August

1000

 

Which of the following statements are true?

  1. Forecast for the number of cases in September is 952
  2. Mean absolute deviation of the data is 212.813
  3. Tracking signal = 5
  4. Tracking Signal = -5

Answer (Detailed Solution Below)

Option :

Scheduling Question 7 Detailed Solution

Concept:

Let the actual cases de denoted as demand (D)

And Forecasted cases be denoted as (F)

\({F_{t + 1}} = \;{F_t} + \;\alpha \left( {{D_t} - {F_t}} \right)\)       ---(1)       

Calculation:

For the month of April, given F =100

Soothing constant (α= 0.8)

By calculation as per (1), the following data is obtained

Month

D

F

ei = Di-Fi

April

140

100

40

May

350

132

218

June

650

306.4

343.6

July

800

581.28

218.72

August

1000

756.256

243.744

September

 

951.25

 

 

Mean absolute deviation (MAD)

\(MAD = \;\frac{{\mathop \sum \nolimits_{i = 1}^5 \left| {{e_i}} \right|}}{5} = 212.8128\)    (option b)

Running some forecast error (RSFE)

Now,

\(RSFE = \;\mathop \sum \limits_{i = 1}^5 {e_i} = 1064.064\)

Tracking signal (TS)

\(TS = \frac{{RSFE}}{{MAD}} = 5\)  (Option c)

সময়সূচী তৈরি Question 8:

Routing __________.

  1. Prescribes the sequence of operations to be followed
  2. Determines the programme for the operation
  3. Is concerned with starting of processes
  4. Regulates the progress of job through various processes

Answer (Detailed Solution Below)

Option 1 : Prescribes the sequence of operations to be followed

Scheduling Question 8 Detailed Solution

Routing lays down the flow of work in the plant. It determines what work is to be done and where and how it will be done.

Taking from raw material to the finished product, routing decides the path and sequence of operations to be performed on the job from one machine to another. The purpose is to establish the optimum sequence of operations.

সময়সূচী তৈরি Question 9:

Find the optical sequence: (duration in hours)

JOBS

A

B

C

D

E

M1

5

1

9

3

10

M2

2

6

7

8

4

  1. BDECA
  2. BCDEA
  3. BDCEA
  4. BEDCA

Answer (Detailed Solution Below)

Option 3 : BDCEA

Scheduling Question 9 Detailed Solution

Use Johnson’s Algorithms solve.

 

 

 

 

 

 

Make a box like this & select the lowest number (say ‘1’ in this case). If the number belongs to ‘M1’ place it on extreme left or else place it on the right side at the box.

B

 

 

 

 

 

Next lowest is ‘2’ on ‘M2’, so place it in the Right

B

 

 

 

A

 

Next is ‘3’ on ‘M1’, so place it on left

B

D

 

 

A

 

Next is ‘4’ on ‘M2’, so place it on Right.

B

D

C

E

A

 

‘c’ is the only Remaining job so place it on the vacant position.

Hence the correct sequence is : BDCEA

সময়সূচী তৈরি Question 10:

 Gantt chart is useful in

  1. Scheduling
  2. Forecasting
  3. Routing
  4. Both (2) & (3)

Answer (Detailed Solution Below)

Option 1 : Scheduling

Scheduling Question 10 Detailed Solution

Explanation:

Gantt chart:

  • Gantt charts are mainly used to allocate resources to activities.
  • Gantt chart is applicable for Production scheduling.
  • The resources allocated to activities include staff, hardware, and software. Gantt charts are useful for resource planning.
  • A Gantt chart is a special type of bar chart where each bar represents an activity. 
  • This chart lists the tasks to be performed on the vertical axis, and time intervals on the horizontal axis.
  • The bars are drawn along a timeline. The length of each bar is proportional to the duration of time planned for the corresponding activity.
  • With the use of this chart, we can check the progress of project with
    • A visual display of the whole project,
    • Timelines and deadlines of all tasks,
    • Relationships and dependencies between the various activities,
    • Project phases

1236986

On Gantt Chart one can easily view

  • ​The start date of the project
  • What the project tasks are
  • Who is working on each task
  • When tasks start and finish
  • How long each task will take
  • How tasks group together, overlap and link with each other
  • The finish date of the project

Get Free Access Now
Hot Links: teen patti all teen patti gold old version teen patti master 2025