Question
Download Solution PDFAs per IS456: 2000, what is period of removal of props to beam and arches which is spanning upto 6 m?
Answer (Detailed Solution Below)
Detailed Solution
Download Solution PDFExplanation:
As per Clause 11.3.1 of IS:456-2000
Type of Formwork |
Minimum Period Before Striking Formwork |
Vertical formwork to columns, walls, beams. |
16 - 24 h (1 Day) |
Soffit formwork to slabs |
3 days |
Soffit formwork to beams |
7 days |
Props to slabs a. Spanning up to 4.5 m b. Spanning over 4.5 m |
7 days 14 days |
Props to beams and arches a. Spanning up to 6 m b. Spanning over 6 m |
14 days 21 days |
Last updated on Jun 2, 2025
-> HPCL Engineer 2025 notification has been released on June 1, 2025.
-> A total of 175 vacancies have been announced for the HPCL Engineer post in Civil, Electrical, Mechanical, Chemical engineering.
-> HPCL Engineer Online application will be activated from 1st June 2025 to 30th June 2025.
-> Candidates with a full-time engineering discipline in the relevant stream are eligible to apply.
-> The selection will be based on a Computer Based Test Group Task and/or Interview. Prepare for the exam using HPCL Engineer Previous Year Papers.